The tendering process for the much-awaited metro line from Silk Board to Kempegowda International Airport is finally taking shape.
Bangalore Metro Rail Corporation Limited (BMRCL) has divided the work into eight segments. Tenders for the construction of the Silk Board-KIA Metro line are likely to be floated by the first week of November this year.
The Silk Board to K.R. Puram line (Phase II A) will be executed in three packages while the K.R. Puram to KIA line (Phase II B) will be implemented in five packages, said officials.
Ajay Seth, Managing Director, Bangalore Metro Rail Corporation Limited (BMRCL), said, “It is a 56-km-long line. We have submitted the tender documents to the Asian Development Bank and are awaiting their nod. We are not going to float the tenders at one go, but once in three months in two to three packages.”
Biltrax Construction Data is tracking this project on their technology platform for their Clients.
For more information reach out to us at (+91) 90826 75827, contact@biltrax.comor visit https://www.biltrax.com/
Discover more from Biltrax Media, A Biltrax Group venture
Subscribe to get the latest posts sent to your email.